FB3.1.0.181. Timer or time-out

Hi,

sometimes my action could not finish operation and FB project waits the action infinitely.
How can I set time-out for my action?

Igor,
igor.zc@gmail.com

Hi Igor,

What action are you using? In FinalBuilder 3 there is nothing you can do but press the Terminate (red) button. If you upgrade to FinalBuilder 5, many actions now have a timeout field where you can set a maximum time to run before the action is automatically failed.

Regards,

Angus

In our night builds we try to build VS6 workspace, but sometimes VS6 is hold and our sequence cannot continue.
And now we have not a possibility to set time-out for this problematic VS6 action.
As I understand FB3 has not a solution for our problem.
understood. seems we should fix the problem with VS6 action.

Igor.

Hi Igor,

That sounds like the best solution for now.

Regards,

Angus